2009 December

Dec 3

FERC Deadline
for Downeast LNG to provide
operational capabilities information
if Maritimes & Northeast Pipeline
will not expand

See the FERC Docket File List requiring this information.

DeLNG's response may be insufficient to satisfy FERC. See DeLNG's 2009 Nov 23 response to FERC's request.

Dec 17

?

Original
Federal Authorization Decision Deadline
for Downeast LNG

The final decision for the Downeast LNG project is scheduled for this date; however, it has been delayed due to Downeast LNG tardiness in submitting FERC-requested information, delaying completing the prerequisite Final Environmental Impact Statement (FEIS).

>> Rescheduled date has not yet been announced <<
as of 2009 Dec 14.